Progress Shines Bright at Reading’s Pagoda: Mayor Morán and Media Tour Landmark Renovations

From City of Reading

On Tuesday, Oct. 28, Mayor Eddie Morán joined members of the media for an exclusive tour of the ongoing rehabilitation work at Reading’s beloved Pagoda.

The tour was led by Capital Projects Manager David Anspach III, who provided an in-depth look at the progress being made to restore and modernize the historic landmark while preserving its rich character and cultural significance. The Pagoda rehabilitation project has reached several major milestones, marking a significant step forward toward reopening the site to the public.

“This restoration brings us one step closer to reopening our city’s most recognizable symbol,” said Mayor Morán. “I’m grateful to everyone working to ensure the Pagoda remains a safe, beautiful, and welcoming space for generations to come.”

Project Progress Highlights

  1. Lighting: All lighting circuits have been installed and tested in daylight. Final connections to the control center and evening testing are pending. Mayor Morán shared his excitement that the lights will flash for Santa in 2026!
  2. Painting: Interior painting has been completed on floors 2 through 6.
  3. Flooring: New flooring installation is underway, currently being completed on floors 6, 5, and 4, progressing downward through the building.
  4. ADA Accessibility: Ground-level bathrooms have been modified for ADA compliance, with new fixtures being installed.
  5. Mechanical Systems: A new hot water heater and boiler system have been installed.
  6. HVAC: The heating, ventilation, and air conditioning system is approximately 75% complete.
  7. Structural Repairs: Foundation wall repairs have been completed.
  8. Exterior Masonry: Grouting of the building’s stone walls is 90% finished, with an anti-graffiti coating to follow.
  9. Scaffolding: Most exterior work on scaffolded sections has been completed, and removal of scaffolding will soon begin.
  10. Fire Safety: All dry-head fire sprinklers have been replaced.

The project is expected to reach substantial completion by early December, with final completion slated for no later than Jan. 2, 2026, per the construction contract.

The post Progress Shines Bright at Reading’s Pagoda: Mayor Morán and Media Tour Landmark Renovations appeared first on BCTV.